• Client: Provincial Road and Urban Development Department
    Consultant: Bank to Bank
    Road Length: 5,000+km
    Earthworks: 181,000 cubic meters
    Concrete: 8,000 cubic meters
    Foundation and sub-foundation: 25,000 cubic meters
    Asphalt: 10,000 tons

Completion project for the improvement of the Holy Defense - Shahid Namjoo intersection and the non-level intersection

Employer:
Hormozgan Province Road and Urban Development Department
Consultant:
Karane be Karane

Follow us

Our extensive resume consists of over 3,500 completed projects.

Our diverse project list includes earthworks, foundation works, tunnel excavations, and more.

Be sure to receive the latest exclusive offers, product releases and much more.

در خبرنامه ما ثبت نام کرده و مشترک شوید و هر ماه تخفیف بگیرید